Mambourin Green Construction Update - Stage 5


19 March 2026

 

Settlement Forecast: Q1 2027

On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Construction Progress: Services
On Track

The detailed design for Stage 5 is expected imminently. This milestone will confirm that all technical engineering plans required before commencing major construction have been formally signed off, ensuring works can move smoothly into the next phase without delay.

Early sewer works, which began at the end of January, are now complete. These works installed the essential underground sewer infrastructure required for the stage. Completing these works early helps maintain program and reduces the risk of civil construction delays.

Civil construction is expected to commence at the end of March, with our contractor already onsite. This marks the shift from planning into active delivery of roads, drainage, services and other core civil infrastructure.

Track your property anytime, anywhere on our new myFrasersProperty app.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.


See more construction updates on



You may also like