To assist you on your property journey we have developed this tracker that can guide you on all the important milestones from when you sign the contract, to construction and reaching a settlement and beyond. Click on the phases below or click and drag left and right to scroll through the milestones.



Disclaimer: Whilst Frasers Property has tried to ensure that the tracking status is up to date, the content provided is ‘as is’ and ‘as available’ and is subject to change.

Certificates of Title Planned : July/August 2025

Construction is well underway. Earthworks are complete. Retaining walls are 90% completed. Deep services (Drainage and pits) are complete and shallow services (power, water, gas) are all approximately 90% complete.

Now that most of the retaining walls and services are complete, roadworks can commence. This is the last major milestone in the construction program and the catalyst for applying for early clearances and then titles.

Earthworks are now complete. Retaining Walls, deep and shallow services are nearing completion.
Roadworks (the last major milestone in the construction program) will commence shortly.
Practical Completion on track for July with Titles to follow.
Latest Construction Update



Recent Stage 9 Updates

It's all here to keep you up to date with the latest news and updates about Stage 9.

View Updates

Track another property

card icon

NOW SELLING

Stage 5

Settlements underway​

Track property

card icon

NOW SELLING

Stage 6C

Certificates of Title available

Track property

card icon

NOW SELLING

Stage 8A

Certificates of Title planned for December 2024

Track property

card icon

SOLD OUT