Botanica Construction Update - The Mews
- Settlement Forecast: Quarter 4 2025
-
On Track
We are currently forecasting The Mews for completion and settlement by Quarter 4 2025. This forecast is subject to weather delays, general construction progress, and receipt of the title registration and occupation certificates. - Construction Progress: In progress
-
On Track
Welcome to your July construction update for your property at The Mews at Botanica.
June had started with a bit of rain, but the construction team is working ahead.
Block 1 (CN8201-CN8205): has had it’s scaffolding removed, with the garages and car court façade being revealed. Internally the stairs have successfully been installed and the internal sheeting progressing nicely.
Block 2 (CN8206-CN8208): we have the first set of kitchen joinery being installed, along with the wardrobes. The first coat of paint has been complete, giving the homes further character.
Block 3 (CN8209-CN8212): internal insulation and sheet to commence over the next few weeks and scaffolding coming down soon, this will allow the team to start the internal car court.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We will continue to update you every month as construction progresses, but in the meantime, if you have any questions, please do not hesitate to email customercarensw@frasersproperty.com.au or call 13 86 88 or +612 9767 2297.
See more construction updates on