Botanica Construction Update - The Mews
- Settlement Forecast: Quarter 4 2025
-
On Track
We are currently forecasting The Mews for completion and settlement by Quarter 4 2025. This forecast is subject to weather delays, general construction progress, and receipt of the title registration and occupation certificates. - Construction Progress: In progress
-
On Track
The team at Botanica has welcomed September with encouraging progress and improved weather conditions.
Works are scheduled to commence in September; this will be a great milestone to be completed and is expected to take a month to complete.
Block 1 (CN8201-CN8205): Bathroom tiling has commenced, and kitchen joinery installation is underway. Internal plasterboard walls are now ready for painting.
Block 2 (CN8206-CN8208): With kitchens and wardrobes installed, flooring measurements are being taken in preparation for installation.
Block 3 (CN8209-CN8212): Scaffolding is scheduled to be removed this month, revealing the full character of the homes and enabling plasterboard installation to begin shortly.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We will continue to update you every month as construction progresses, but in the meantime, if you have any questions, please do not hesitate to email customercarensw@frasersproperty.com.au or call 13 86 88 or +612 9767 2297.
See more construction updates on