Berwick Waters Construction Update - Stage 11
- Settlement Forecast: June 2026 – August 2026
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.
- Construction Milestone: Services
-
On Track
Civil works in Stage 11 are progressing very well. Installation of the sewer and drainage pipes is complete. Installation of the watermains is now underway and will be the key task for the next couple of weeks. Following the completion of the watermains, our contractor will start to work on the base levels of the roads.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on