Berwick Waters Construction Update - Stage 11
- Settlement Forecast: April 2026 – May 2026
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.
- Construction Milestone: Roadworks
-
On Track
We're pleased to advise that civil works in Stage 11 are progressing well and are ahead of program. Settlements are now expected in April - May 2026.
The electrical works and telecommunication works are now complete. The footpath works are currently underway.
Once the footpath works are complete, the stage will be topsoiled, after which electrical service audits can be scheduled with the relevant authority.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on