Mambourin Green Construction Update - Stage 2


16 October 2025

 

Settlement Forecast: Feb-Mar 2026

On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions.

Construction Progress: Roadworks and Services

 

We’re please to inform that road capping layer works are almost complete, forming a stable foundation for the internal road network and supporting the next phase of pavement construction.

AG drains and conduits will commence shortly to support effective subsurface drainage and underground utility service provision across the site.

Subbase FCR (Fine Crushed Rock) works for the lower road pavement are set to commence following the completion of AG drains, marking a significant milestone in the delivery of internal infrastructure and enhancing site accessibility.

Track your property anytime, anywhere on our new myFrasersProperty app.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

We're available to discuss any questions or concerns you may have regarding your coming settlement.


Contact Centre Frasers Property Australia

See more construction updates on



You may also like