Mambourin Green Construction Update - Stage 2
- Settlement Forecast: April 2026
-
On Track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions. - Construction progress: Roadworks
-
On Track
We’re pleased to advise that electrical reticulation works are now complete, with the underground power network and public lighting infrastructure fully installed. This milestone delivers the essential services that will supply reliable electricity and street lighting to future homes within the development.
Communication reticulation works, including the installation of Opticomm infrastructure, have also been completed. With this groundwork in place, the stage is prepared for future high-speed internet services, supporting a well-connected community once homes are built.
Concrete works, involving the construction of footpaths and driveway crossovers, are now underway. These works help define the pedestrian layout and establish the formal access points that will serve future homes.
Topsoiling is scheduled to commence next, with placement across nature strips and lots. This work prepares the ground for future landscaping and establishes the final surface levels, contributing to the overall presentation of the development.
Track your property anytime, anywhere on our new myFrasersProperty app.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on