Certificates of Title: March 2026

Stage 11 Forest Walk – Construction is progressing well and on program with main works on site concentrated around installation of water and drainage services, retaining walls and underground power. Powderbark Avenue remains closed whilst construction works are in progress.

Sewer Reticulation 95% complete.
Stormwater Drainage and Water Reticulation & Gas 85% complete.
Retaining Walls 50% complete.
Latest Construction & Community Update

Track my Property

To assist you on your property journey we have developed this tracker that can guide you on all the important milestones from when you sign the contract, to construction and reaching a settlement and beyond. Click on the phases below or click and drag left and right to scroll through the milestones.

card icon

SOLD OUT

Rivers Edge Stage 5

Certificates of Title available

Track property

card icon

SOLD OUT

Forest Walk Stage 9

Certificates of Title Available

Track property

card icon

SOLD OUT

Forest Walk Stage 10

Certificates of Title available

Track property

card icon

SOLD OUT

Completed Stages

For build documents on completed stages please follow the link

Build information