To assist you on your property journey we have developed this tracker that can guide you on all the important milestones from when you sign the contract, to construction and reaching a settlement and beyond. Click on the phases below or click and drag left and right to scroll through the milestones.



Disclaimer: Whilst Frasers Property has tried to ensure that the tracking status is up to date, the content provided is ‘as is’ and ‘as available’ and is subject to change.

Certificates of Title Expected: March 2026

Construction is 97% complete. Practical Completion (PC) is on track for the 11th February 2026. Following PC, any identified defects or omissions will be rectified to the City of Mandurah’s satisfaction. We anticipate Western Power to energise the stage in April 2026. However, this is subject to Western Power confirming this date. We will email our Stage 11 buyers once a date is confirmed. The Stage 11 Park design is with City of Mandurah for approval. We anticipate works commencing in March 2026.

Final Pegging will be complete by the 30th Jan, with lot signs already installed.
Stage 11 park works to commence in March/April 2026.
Western Power handover and energisation dates to be confirmed.
Latest Construction & Community Update

Track my Property

To assist you on your property journey we have developed this tracker that can guide you on all the important milestones from when you sign the contract, to construction and reaching a settlement and beyond. Click on the phases below or click and drag left and right to scroll through the milestones.

card icon

SOLD OUT

Rivers Edge Stage 5

Certificates of Title available

Track property

card icon

SOLD OUT

Forest Walk Stage 9

Certificates of Title Available

Track property

card icon

SOLD OUT

Forest Walk Stage 10

Certificates of Title available

Track property

card icon

SOLD OUT

Completed Stages

For build documents on completed stages please follow the link

Build information