Berwick Waters Construction Update June 2022

Stay informed with the latest construction progress at Berwick Waters.


29 June 2022

 

On-Site Progress

While the recent wet weather has delayed some work on site, we're happy to announce that service testing is well underway in Stages 1, 2 and 3.

This month, we passed the sewer and water service tests in Stage 1, while Stage 2 and Stage 3 sewer and water service tests are in progress. Next up for Stage 1, we’re completing pavement around the Riverstone and Honour Avenue roundabout. On Stage 2, all kerbs and gutters have now been completed, while footpaths and driveways are close to completion in Stages 3 and 15. In Stage 5, electrical and communications trenching is underway and planned for completion this month.

Next month will be focussed on finalising service testing and connection in Stage 15.