The Quarry Construction Update – Release Seven
- Settlement Forecast: Q4 2026
-
On track
Please note that the anticipated timeframe for settlement is indicative and subject to change due to the civil works program, external authority involvement and weather conditions. - Construction Progress: Services
- Commenced
Your latest construction update for Release 7 at The Quarry
Construction is continuing to progress well, with stormwater and sewer infrastructure works currently underway. We’ve recently completed the removal of the existing roadway to Ridgeline Way, and earthworks to establish the final lot levels were successfully completed in August 2026.
During September, crews will continue installing key services, including stormwater and sewer infrastructure. Construction of retaining walls will also commence, with Adbri retaining walls being installed between selected allotments.
Settlement is currently anticipated in Q4 2026, subject to weather conditions and construction progress. We’ll continue to keep you updated with monthly progress reports as we move closer to completion.
If you have any questions, our Customer Care team is here to help. Please feel free to contact us using the details below.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
We're available to discuss any questions or concerns you may have regarding your coming settlement.
See more construction updates on