myFrasersProperty 13 38 38
myFrasersProperty 13 38 38

Bradmill Yarraville Construction Update - Monfort Townhomes 2B


27 March 2026
Settlement Forecast: Q4 2026

On Track

Construction Progress: Construction in progress
On Track
Stage 2B: Monfort Townhomes

Homes 201–204 are nearing completion internally, with tiling, joinery, benchtops and marble splashbacks all in place, while externally topsoil has been imported and planting is due to commence shortly.

Homes 214–220 and 221–226 are progressing well, with external cladding underway and plasterboard installation commenced.

Homes 233–241 have completed brickwork, with rendering ongoing, cladding to commence soon, and services rough-in completed.

Homes 227–232 have completed framing, with services rough-in and external cladding currently in progress.

It’s a good time to start discussing your settlement with your bank and solicitor if you haven’t already. Keep them updated and let them know of any changes to your settlement forecast in the coming months – this helps your finance and legal teams stay prepared and ensures a smooth settlement process.


Tina Wu Senior Customer Care Consultant Melbourne

See more construction updates on



You may also like