Shell Cove Construction Update - Meridian Homes


11 September 2025

 

Settlement Forecast: Q 4, 2025/Q1, 2026

On Track

We anticipate settlements to occur from Q 4, 2025/Q1, 2026

Construction Progress: In progress
On Track

Welcome to the latest Construction Update.

We’re pleased to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.

Our teams have been working diligently, making significant progress, and here’s what’s been happening across the different homes:

Home 3501–3504

  • External finishes are almost complete.
  • Scaffold dismantle is imminent.
  • Linings and internal fit-outs are ongoing.
  • Waterproofing and tiling works are underway.
  • Landscaping preparation is being planned.
  • Settlement is forecast for Late Quarter 4, 2025.

Homes 3502–3506

  • External finishes are almost complete.
  • Scaffold dismantle is imminent.
  • Linings and internal fit-outs are ongoing.
  • Waterproofing and tiling works are underway.
  • Landscaping preparation is being planned.
  • Settlement is forecast for Late Quarter 4, 2025.

Homes 3507–3508

  • External finishes are almost complete.
  • Internal insulation and linings have commenced.
  • Balcony glazing and feature screen installation are imminent.
  • Settlement is forecast for Quarter 1, 2026.

Homes 3509–3512

  • External brickwork and cladding are continuing.
  • Balcony glazing and feature screen installation are imminent.
  • Internl insulation and linings have been delivered.
  • Settlement is forecast for Quarter 1, 2026.

Please accept marketing cookies to view this content.


Prepare for settlement


Use myFrasersProperty app to track your property

Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.

Step 1:

Click here to request your account.

Step 2:

Activate your account following this helpful video guide.

Step 3:

Download myFrasersProperty from your app store.


Help is always available

Our team remains dedicated to delivering your home with the highest quality standards. Should you have any questions or require further information, please do not hesitate to contact our Customer Care team.


Site Safety

We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.


Silvana Stojanovski Customer Care Coordinator Frasers Property Australia

See more construction updates on



You may also like