Shell Cove Construction Update - Meridian Homes
- Settlement Forecast: Q1, 2026
-
On TrackWe anticipate settlements to occur from Q1, 2026
- Construction Progress: In progress
- On Track
Welcome to the latest Construction Update.
We’re pleased to keep you informed about how the project is progressing, give you insights into the construction process and ensure you’re up to date with the development of your new community.
Our teams have been working hard, and steady progress continues across the Meridian homes. We have recently encountered some resourcing delays beyond our control, this has led to slight shifts in settlement timelines. Despite these challenges, our team remains fully committed to delivering each property to the highest standard.
Works are progressing well, and here’s an update on what’s been happening across the homes:
Home 3501-3504
- Internal fit-outs are progressing well.
- Tiling works are largely complete, with final grouting and touch-ups underway.
- Painting and final finishes have commenced.
- Landscaping works have commenced, with feature fencing currently in fabrication.
- Garage works are approaching completion, with scaffold dismantle booked shortly.
- Settlement forecast: Quarter 1, 2026.
Homes 3505-3506
- Internal fit-outs are progressing well.
- Kitchen installation is now complete.
- Tiling works are largely complete, with final grouting and touch-ups underway.
- Painting and final carpentry/joinery works are underway.
- Landscaping works have commenced, with feature fencing currently in fabrication.
- Garage works are approaching completion, with scaffold dismantle booked shortly.
- Settlement forecast: Quarter 1, 2026.
Homes 3507-3508
- External cladding and finishes are now complete.
- Scaffold dismantle has commenced.
- Balcony glazing and feature screen installation have been completed.
- Internal linings and insulation are complete, with internal fit-outs well underway.
- Waterproofing and tiling to wet areas have commenced.
- Garage works are progressing, with roof truss installation commencing shortly.
- Settlement forecast: Quarter 1, 2026.
Homes 3509-3512
- External brickwork and cladding works are complete.
- Scaffold dismantle will commence shortly.
- Balcony glazing and feature screen installation are underway.
- Internal insulation and linings have commenced and will continue over the coming period.
- Garage works are progressing, with roof truss installation commencing shortly.
- Settlement forecast: Quarter 1, 2026.
Prepare for settlement
Use myFrasersProperty app to track your property
Follow three easy steps to create your account and start tracking your property progress and information no matter where you are.
Step 1:
Click here to request your account.
Step 2:
Activate your account following this helpful video guide.
Step 3:
Download myFrasersProperty from your app store.
Help is always available
Our team remains dedicated to delivering your home with the highest quality standards. Should you have any questions or require further information, please do not hesitate to contact our Customer Care team.
Site Safety
We understand and share your growing interest and excitement as your new home begins to take shape. We are also highly committed to the safety of our purchasers and members of our construction team. Hence, we would like to remind you that at no time are any of our purchasers permitted to enter the construction site or fenced compounds, as doing so places you at risk of accident or injury.