Bradmill Yarraville Construction Update - Monfort Townhomes 2A


10 December 2025
Settlement Forecast: Q3 2026

On Track

Construction Progress: Construction in progress
On Track
Stage 2A: Monfort Townhomes

Construction continues to progress well across this stage.

Homes 205–207: Brickwork has been completed, services rough-in are underway, and plastering has now begun.

Homes 208–213: Cladding works are completed, plasterboard has commenced in these homes.

Homes 242–247: Framing are completed, and roofing has commenced.