Bradmill Yarraville Construction Update - Monfort Townhomes 2A
- Settlement Forecast: Q3 2026
-
On Track
- Construction Progress: Construction in progress
-
On Track
Stage 2A: Monfort Townhomes
Homes 205–207 have completed joinery installation, stone benchtops, and services fit-off, with external areas prepared for planting following topsoil placement. Homes 208–213 are in the final defects stage internally, with appliances installed and commissioned, and fencing due to start shortly. Homes 242–247 are progressing internally with joinery installation underway and benchtops in place. Landscaping works expected to commence soon.
It’s a good time to start discussing your settlement with your bank and solicitor if you haven’t already. Keep them updated and let them know of any changes to your settlement forecast in the coming months – this helps your finance and legal teams stay prepared and ensures a smooth settlement process.