Bradmill Yarraville Construction Update - Monfort Townhomes 2A


27 March 2026
Settlement Forecast: Q3 2026

On Track

Construction Progress: Construction in progress
On Track
Stage 2A: Monfort Townhomes

Homes 205–207 have joinery and stone benchtops installed, with topsoil imported externally and areas ready for planting.

Homes 208–213 are progressing well internally, with joinery and tiling complete and flooring now being installed.

Homes 242–247 have completed external cladding works with scaffolding removed, while internally plasterboard is installed and joinery is underway.

It’s a good time to start discussing your settlement with your bank and solicitor if you haven’t already. Keep them updated and let them know of any changes to your settlement forecast in the coming months – this helps your finance and legal teams stay prepared and ensures a smooth settlement process.


Tina Wu Senior Customer Care Consultant Melbourne