Bradmill Yarraville Construction Update - Monfort Townhomes 2A
- Settlement Forecast: Q3 2026
-
On Track
- Construction Progress: Construction in progress
-
On Track
Stage 2A: Monfort Townhomes
Progress across these homes continues to advance well. Homes 205–207, internal tiling is currently underway, with joinery installation close to completion. Preparation for external landscaping has also commenced. Homes 208–213, tiling has been completed and joinery fully installed. Works are now progressing into floor covering preparation. For Homes 242–247, metal cladding works are nearing completion, with scaffold removal scheduled for the end of February. Internal plasterboard installation is on track for completion by the end of March, and waterproofing works will commence shortly.