Planned Settlement: Q3 2026

Monfort Townhomes 2A

Homes 205–207: Joinery installation is complete and stone benchtops are in place. Services fit-off has been finalised. Externally, topsoil has been imported and areas are prepared for planting.
Homes 208–213: Internally, the builder is progressing through the final defects stage. Appliances have been installed and commissioned, with fencing installation due to commence shortly.
Homes 242–247: Internally, joinery installation is underway, with benchtops already in place. Landscaping works are expected to commence shortly.